Proper
vehicle access to the silo is essential. With vehicles up to 15 metres long and 40 tonnes
in weight, adequate ground strength and manouvering room are required. |
 |
Lighting is
required if deliveries are to be made outside daylight hours. |
 |
Advance
planning will facilitate delivery at specified times. |
 |
The level of
cement in the silo should always be checked before filling begins. |
 |
Ensure that
the time between filling of the silo and shutting off the cement supply is kept to a
minimum to avoid overfilling. |
 |
The bulk
density of fresh cement varies from 1000 to 1350 kg/m3. The capacity of a silo
may therefore be reduced by over 25% with freshly areated cement. It is therefore
advisable to be conservative when estimating the weight of cement required to fill a silo. |